The application — one document, two parts: the project narratives (Diane’s file of August 20, with her corrections of August 23) and the City’s form, section by section.
1316 Bozeman St. is an historic building, built in the 1880s as a warehouse and retail store for groceries and hardware. It has since been occupied by several owners, who used the venue mainly as grocery storage for Helena. For the last 80 years it has been occupied by a family-owned business: Capital Transfer and Storage, a residential and commercial moving, packing and storage business also offering to the community warehousing and shipping services.


Its new lessee and future owner, Stephen Banker, of Joshua Tree Cabinetry, owns a thriving business - currently in the Valley, but moving to 1316 Bozeman St., the heart of Helena. Plans to renovate the building: restoring the exterior to its historical facade while renovating its structural integrity and strength so that it can be enjoyed by the district for generations to come. JTC is a light industry, exactly what the area is zoned for. Mr. Banker puts his heart and soul into his work, into his employees and has given back to the community throughout the years. His attention to detail and his creativity will help bring the building back to its historical look and feel.


Joshua Tree Cabinetry is a high quality business. They have contracted with local companies to do much of the work on the building. These will have the opportunity to enjoy the businesses, coffee shops, etc. available in the area. There will be an historical information display inside the building, showing the various owners of the building as well as the story of Capital Transfer and Storage, for anyone to enjoy. Two elements to be added are a sidewalk water spicket, and air (for tires) for cyclists coming through the district.
The goal is adaptive reuse and structural strength: to renovate and restore the integrity of the building and its original, historical look and feel. Many aspects of the building need replacement and/or restoration: overhead doors, broken stonework and deteriorated pointing, all doors, all windows and panes (some of which are cemented over), corroded window wells, barn doors in the back of the building (one of which is cemented over). Gutters over the stonework will need to be built for the preservation of the stone walls and mortar: to prevent freeze/thaw damage, mortar erosion and efflorescence (which indicates that moisture is penetrating or moving through the masonry) as well as preserving the foundation of the building. Per Karson Klass, the contracted mason, “repointing will take place on the bottom portion of the building due to lack of gutters and water splash deteriorating the mortar.” Repointing also needs to be completed on all areas of the stonewall (per a sampling of photos below). JTC is hoping to replace the sign on top of the warehouse, though it has been a challenge to find a company to commit to it. Karson Klass plans to match chemical / materials balance of the original mortar.
JTC has already restored the clapboard siding of the office exterior (see photos above). Windows will be replaced with energy-efficient windows.
The handicapped ramp needs to be extended to meet code. The restoration will both enhance the historic appeal of the building as well as its structural sturdiness and usefulness both in the front and the back of the building.






Deterioration in pointing and window wells on front. Windows need replacement.



Front overhead doors to be replaced. One of 2 man doors to be replaced.



Barn doors, concrete-covered windows and doors to be rebuilt along the back of the building.






Just a few samples of holes, cracks and deterioration along stonewall.
Per above, Joshua Tree Cabinetry complies with many of the RURD goals.
Not only is JTC restoring the original look of 1316 Bozeman St., but it is also restoring its structural integrity so that it will retain its historic look and feel for years to come. Pam Attardo and the Historical Society have provided interesting information, maps and photos which we will seek authorization to use as a historical display showing maps, photos and information about the history of the building and companies that have owned it throughout the years. With John Horne’s blessing, JTC will brighten and restore the mural painted on the smaller building on the property.
We have already reached out to BNSF and have begun correspondence with the gentleman in charge of 1316 Bozeman St. property.
Joshua Tree Cabinetry, a thriving business, will bring new business and vitality into the venue. (JTC is currently located in Helena valley.)
Joshua Tree Cabinetry, a light industry, will fit perfectly into the zoning of the area.
JTC is definitely interested in providing opportunities for high school and Helena College students to be trained in carpentry and woodworking. JTC has worked with a school in the district and has already hired a high school student who has had a secure position with the company for 4+ years. JTC has also contributed to the community in other ways.
Two elements to be included in the plans are a sidewalk water spicket, air (for tires) for cyclists coming through the district, as well as a display of the historical timeline of use for the building. The mural of the RURD, painted on a smaller building on the property, is also going to be restored.
The handicapped ramp needs to be extended to meet ADA code. Other elements to be included in the plans are a sidewalk water spicket, and air (for tires) for cyclists coming through the district.
Joshua Tree Cabinetry complies with the City’s Zoning Requirements, being light industry/manufacturing. Mr. Banker plans to remove or trim the foliage around the building for utility and aesthetics. He has hired a contractor to repoint and repair the stonework, restoring its integrity and historical appeal. He has contracted to replace the overhead doors, windows, man doors. He will be restoring the window wells, remove concrete from the windows (back and front) and doors in the back, and rebuild barn doors at the back of the building. For the preservation of the stone work and mortar he will contract a gutter over the stonework. To meet ADA requirements, he will also rebuild the handicapped ramp and entrance. Mosaic Architecture is soon to get back to us regarding engineering standards.
There will be no removal of structures, nor demolition of properties.
No tenants are to be dislocated as a result of the project, since there are no tenants living on the premises.
Mr. Banker has already begun work, investing some of his own funds and capability, reflecting his interest and intentions to follow through with the project. (**see photos above) He has obtained a line of credit from a home equity loan of up to $250,000.
As seen by what Mr. Banker has already accomplished in beginning renovations of the building, he is talented, creative and accustomed to working with contractors.
The project is anticipated to be completed by the end of 2027, though much of the work has begun or will begin in 2026.
All taxes are up to date. (See copy of 2025 property taxes.)
The overall restoration will enhance both the historic appeal of the building as well as its structural sturdiness and usefulness both in the front and the back of the building.
The adaptive reuse of the building involves bringing in a thriving business, Joshua Tree Cabinetry, its customers and employees to the RURD. Along with the contractors and workers on the project, it will also bring patronage to businesses in the community. Renovations to the building’s exterior and mural will renew the appeal of the building, benefiting the district.
Mr. Banker has already expended some of his own capital, reflected in the photos above. He will continue to invest in the renovation / restoration project as needed. It is a prudent investment of public funds within the urban renewal district as it is reviving the original, historic façade of the building and adding appeal to the District. Also, the work being done will strengthen the building structurally for years to come.
The renovation of the building means that JTC is hiring contractors from Helena, and their workers and may very well be hiring more employees due to the increased space and work capacity of the building. This will also increase patronage to the businesses in the area.
See photos above, which show that work already begun reveals attractive, historic stonewall and clapboard. A mural illustrating the District’s history is painted on a smaller building on the property, and will be renewed. The continued renovation of the building will hopefully inspire other building owners in the District to renovate their properties as well, to enhance the historical feel and attractiveness of the area.
This project will bring increased tax revenue to the community, preserve and reveal this historic building for the community to enjoy and possibly to inspire others in the area to renovate their buildings to reflect the historicity of the District. It will bring a new business into the area, and it will increase the activity in the surrounding area.
The project’s impact on the area will be minimal as far as safety concerns, pollution, traffic congestion and pedestrian access. There may be noise and dust for a few days while removing mortar, and concrete from windows and doors.
The goal of the project being proposed is to rediscover the historic façade of this building. JTC will need to restore windows, doors and the entire exterior – not only to reveal its historicity, but also to rebuild and restore its structural integrity. The above photos reveal a stone wall, clapboard siding and other elements which had been hidden from view until recently. Joshua Tree Cabinetry plans to (contract out to) repoint and restore the stone wall to its original appeal and durability, remove cement from in front of some of the windows and doors and replace the windows and doors. Thus, JTC is bringing the building to life and closer to its historical appeal for generations to come. JTC will be bringing its business to the building, so bringing a thriving business into the area.
Mr. Banker is adapting 1316 Bozeman St. from a warehouse to a viable cabinetry business while restoring its historic, aesthetic appeal and creating value to the surrounding Railroad District. It will reveal and retain its historical facade, as well as strengthen the integrity of the building to prolong its structural integrity for years to come. Included in the restoration will be energy-efficient windows. There will be no density nor infill in this project.
JTC is planning to add a water spicket and air (for tires) for public use, as well as restore the mural on the smaller building on the property. Also, the handicapped ramp leading to the office will be extended for ease of use, and the entrance will be enhanced for ease of use.
We have no plans for housing.
We are in compliance with 7-15-4288, section….. (I am still studying this )
| Category | Item | Amount |
|---|---|---|
| Construction | Office windows — glass + labor/materials (Custom Glass + JTC) | $6,960 — quotes expire Aug 27; file Aug 28 |
| Construction | Front shipping windows — glass + labor/materials | $5,946 |
| Construction | Basement windows — weather protection only; basement not occupied (Every Window glass; Stephen installs) | $2,704.59 |
| Construction | Remove concrete from 8 covered windows (front 3, back 5) | $1,600 |
| Construction | Restore window encasements — frame and glass, 8 | $6,000 |
| Construction | Remove concrete from 2 doors + restore doors (back; one rear barn door is filled with concrete) | $6,000 |
| Construction | Window wells, 2 (front) | $1,000 |
| Construction | Bifold barn / double-hinged doors, 3 (back) | $5,400 |
| Construction | Masonry + repointing, front and back (Karson Klass) | $6,300 |
| Construction | Gutters over the stonework only (not the entire building; not aluminum; steel suspected) | $14,100 |
| Construction | ADA / handicap entrance — ramp and landing (door stays off) | $5,000 — quoted Aug 23; get paper in the packet |
| Construction | Overhead doors, 5 (Overhead Door Co. of Helena, Est. #710 — approved Jul 21) | $19,220 — deposit $11,532 due Sept 8 |
| Construction | Mural restoration — scaffolding, paint, labor (with John Horne's blessing) | $2,500 |
| Construction | Graffiti removal (2 instances) | [NEED bid] |
| Other | Disposal of removed materials | $1,200 |
| Other | Air and water for cyclists (public sidewalk gift) | $750 |
| Soft costs | Permits, surveys, design | [NEED] |
| Working priced total | August 23 from Diane + $5,000 handicap entrance tonight — graffiti-wash bid still open; basement glass priced, Stephen installs | $84,680.59 |
| Total | Total project development cost | [Open — graffiti wash, soft costs; ramp now $5,000] |
| Line | Amount |
|---|---|
| Applicant / private investment — about $28,000 already spent (Diane, Aug 23), plus a home-equity line of credit of up to $250,000 | ~$28,000 in + up to $250,000 |
| Other funding sources (not this application): Big Sky Trust Fund (up to $5,000/new job) · MT Historic Preservation Grant (March 2028 cycle) · historic tax credits (owner side). Downtown HURD / BID façade is a different district — not this ask. | Pipeline — not this filing |
| TIF request (≤ 50% of eligible exterior) | Railroad District only — working priced exterior $84,680.59; City match at half would be about $42,340; graffiti wash still open |
| Total project financing | [Open — follows the completed cost worksheet] |
| Objective | Answer (from the draft + research) |
|---|---|
| (a) Tax generation | A closed warehouse becomes a working shop. Customers, employees, and suppliers on Bozeman. Restoration contractors buy in the district. Market value $716,000, current. |
| (b) Public/private investment | About $28,000 already in, plus up to $250,000 on the home-equity line. Public money, if awarded, is asked only for the public face. Interior shop stays private. |
| (c) Job creation | [NEED two numbers from Stephen — people at Joshua Tree now, people planned at 1316.] Local contractors for the restoration. Do not guess. |
| (d) Investment spin-off | The stone is already visible again. The mural will be renewed. A cared-for building is the example other owners can see from the sidewalk. |
| (e) Cost-benefit | A modest public share of the exterior keeps a contributing warehouse in use, a craftsman on the street, and a piece of railroad Helena that can be read from the sidewalk. |
| (f) Health & safety | Ordinary rehabilitation: some noise and dust for a few days. Wells and filled openings made sound. Gutters over the stonework shore up deterioration. Ramp meets ADA. Cyclists gain water and air. |
| (g) Historic preservation | Let the warehouse be seen as a warehouse again: stone pointed and protected, openings opened, industrial windows, barn doors working, mural kept. Historical Society maps in the interior display only with authorization. |
| (h) Density / infill / reuse | Reuse, not infill. No added density. No new structure. A warehouse becomes a cabinetry shop behind the same walls. |
| (i) Cost of public services | No new water/sewer or street work. Sidewalk spigot, tire air, mural, ramp — gifts on the existing public way. |
| (j) Housing | None proposed. |
| (k) Conformance (MCA 7-15-4288) | See section 3.k below — completed from the statute Diane provided. |