COST & FINANCING WORKSHEET (ARCHIVE)
1316 Bozeman — this sheet is stale
Do not file from this page. Live priced board as of Aug 23 night: $84,680.59 including handicap entrance $5,000. See the one-page board and application.html.
The table below is the early worksheet (vinyl placeholders, open bids). Kept as lineage only.
Construction / Rehabilitation (exterior focus)
| # | Category | Known / estimate | Source | TIF-eligible? |
|---|---|---|---|---|
| 1 | Office windows (provisional vinyl quote) | $5,560 | Custom Glass #26416 | Pending strategy |
| 2 | Front shipping windows (provisional vinyl quote) | $4,746 | Custom Glass #26433 | Pending strategy |
| 3 | Concreted openings reopen + restore (8 windows + 1 door) | $[NEED] | Bid required | Yes (target) |
| 4 | Window wells repair/rebuild (3+) | $[NEED] | Bid required | Yes (target) |
| 5 | Man doors (3) | $[NEED] | Bid required | Yes (target) |
| 6 | Rear barn / double doors (2) | $[NEED] | Bid required | Yes (target) |
| 7 | Masonry + repointing | $[NEED] | Bid required | Yes (target) |
| 8 | Rear gutters | $[NEED] | Bid required | Yes (target) |
| 9 | ADA ramp | $[NEED] | Bid required | Yes (target) |
| 10 | Overhead / rolling door | $[NEED] | Bid required | Confirm |
| 11 | Basement openings (if any beyond wells) | $[NEED] | Depends on use | Confirm |
| 12 | Paint / finish at openings | $[NEED] | Bid / allowance | With parent scopes |
| 13 | Disposal / haul-off | $[NEED] | Bid required | Likely |
| 14 | Permits / soft costs | $[NEED] | City fee schedule | Confirm |
| Subtotal construction | $[NEED] | |||
| Professional services (design/docs) | $[NEED] | Confirm | ||
| TOTAL PROJECT DEVELOPMENT | $[NEED] |
Financing
| Source | Amount |
|---|---|
| Applicant / private investment (cash + interior + prior) | $[NEED] |
| Other grants (if any) | $[NEED] |
| TIF request (≤ 50% of eligible) | $[NEED] |
| Total financing | $[NEED] |
Notes
- Vinyl window totals above are placeholders pending Window Strategy Memo path (wood vs vinyl).
- Do not incur TIF-matched costs before approval.
- Prevailing wage may apply to certain public-scope items over $25k (see form note) — ask staff.